Big Night, Big Lift. Joll Road Precast Install.
.jpg)
OCTOBER 2025
Nort exactly a nine-to-five job
A massive two-crane lift in the wee hours.
​
While most of the region slept, our install team was wide awake and hard at work on Joll Road, executing a major overnight precast install alongside TW Group.
With two cranes on site including a 90-tonne powerhouse and 20-tonne panels to lift, this was no small feat. The scale was massive, the coordination tight, and the margin for error non-existent.
Thanks to meticulous planning and seamless teamwork, the job was completed safely and efficiently, with the road fully cleared and reopened by 4:30am - minimising disruption to the public and delivering another win for our team.